List of EPC general contractor projects implemented by PC1 Group

Rate this post

PC1 Group has completed many EPC contracts for power projects ahead of schedule and with excellent quality in recent years thanks to its unique traditional advantages, professional capability, and experience in conducting large-scale construction and installation projects. Many projects have been finished and invigorated at the regional level thanks to the efforts of international investors.

Introduction of EPC PC1 general contractor

EPC general contractor

PC1 Group has always had great accomplishments as a leader in the field of electrical construction and has extended into other fields, as proven by national key projects with valuable products and an international level of excellence.

To achieve its vision of becoming one of the “Top 5 areas in the field of EPC general contractor for power grid and energy investment,” the company not only focuses on the domestic market, but also directs resources to expand the field of power construction and installation to markets in Southeast Asian countries.

PC1 Group is the only unit in Vietnam that can design, produce, and manufacture steel structures (single-body steel columns and tubular steel columns) to fulfill the needs of customers, in addition to general contractor management. The domestic market as well as international exports are critical.

With the mission of “constantly creating smart and modern electrical works integrating the national and regional grid systems,” PC1 Group claims to be growing at a rapid and sustainable rate using current platforms.

See more: Professional and prestigious EPC general contractor in Vietnam

List of EPC general contractor projects implemented by PC1 Group

Power plant projects

2018 – 2020 Period

Dau Tieng Solar Power Project – 500 MW

PC1 Group as EPC general contractor for Dau Tieng solar power project

The Dau Tieng Solar Power Project started in June of 2018 and was completed in March of 2019. This is regarded as Southeast Asia’s largest clean energy project. Power China Huadong Engineering Corporation Limited is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Dau Tieng Solar Power Project

BIM2, BIM3 solar power project – 300 MWp

The BIM2 and BIM3 solar energy projects began in June 2018 and ended in April 2019. In 2021, these two factories are among the top ten most typical renewable energy projects in Vietnam. The BIM Group and the AC Energy Group are the project’s investors. PC1 conducts legal services, technical design, procurement, construction, development, manufacture, installation, testing, operation, and COD for the power plant as part of this project.

See more: BIM2, BIM3 solar power project

Phu My solar power plant project – 330MW

Phu My solar power epc general contractor

The construction of the Phu My solar power plant was launched in May 2020 and finished in December 2020. The project has a total capacity of 330MW installed. The Vision Energy Development Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Phu My solar power plant project

Ninh Phuoc solar power plant project 6.1 & 6.2 – 58.3 MWp

The construction of the Ninh Phuoc 6.1 and 6.2 solar power plants began in December 2018 and was finished in June 2019. The overall installed capacity of the project is 58.3 MWp. The Ninh Thuan Renewable Energy and Agriculture Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Ninh Phuoc solar power plant project 6.1 & 6.2

My Son – Hoan Loc Viet solar power plant project – 50MWp

The My Son – Hoan Loc Viet solar power plant project began in November 2018 and finished in May 2019. The project has a total capacity of 50 MWp installed. Hoan Loc Viet Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: My Son – Hoan Loc Viet solar power plant project

DaMi solar power plant project 

Dami solar power-epc general contractor

The construction of the DaMi solar power plant began in June 2018 and ended in May 2019. The project has a total capacity of 47.5 MWp installed. Power Generation Corporation 1 is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, and installation, as well as testing, commissioning, and COD for the power plant in this project.

See more: DaMi solar power plant project 

Bach Khoa – A Chau solar power plant project

The construction of the Bach Khoa – A Chau solar power plant began in December 2018 and was finished in June 2019. The project has a total capacity of 30 MWp installed. Sungrow Group is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Bach Khoa – A Chau solar power plant project

Tri Viet solar power plant project

The construction of the Tri Viet solar power plant began in December 2018 and was finished in June 2019. The project has a total capacity of 30 MWp installed. Sungrow Group is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Tri Viet solar power plant project

BMT solar power plant project

bmt solar power epc general contractor

The construction of the BMT solar power plant began in October 2018 and was finished in April 2019. The project has a total capacity of 30 MW installed. AC Energy Corporation is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: BMT solar power plant project

Nhi Ha solar power plant project

The construction of the Nhi Ha solar power plant began in February 2019 and was finished in June 2019. The project has a total capacity of 50 MWp installed. Bitexco Energy Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant in this project.

See more: Nhi Ha solar power plant project

Phuoc Thai 1 solar power plant project

The work of the Phuoc Thai 1 solar power plant began in September 2019 and will be completed in June 2020. The project has a total capacity of 50MWp installed. Bitexco Energy Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Phuoc Thai 1 solar power plant project

Phan Lam 2 solar power plant project

The Phan Lam 2 solar power plant began in June 2020 and will be completed in November 2020. The project has a total capacity of 49 MWp installed. BBG Group is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, and operation for this project.

See more: Phan Lam 2 solar power plant project

Project of 110kV-63 MVA Substation Project Dam Nai Wind Power Plant 2

The project to build the Dam Nai 2 Wind Power Plant Transformer Station began in May 2018 and was finished in September 2018. The Dam Nai 110kV substation is equipped with a 63MVA 115/23/6.3kV transformer, three 110kV circuit breakers, and a series of 22kV medium voltage cabinets with nine compartments, etc. The Blue Circle is the project’s investor. PC1 is the general contractor for the Dam Nai Wind Power Plant project, implementing Package E03 Supply and Construction of a 110kV 63 MVA Substation.

See more: Dam Nai Wind Power Plant Project

Dai Phong Wind Power Plant project

dai phong wind power

The project for the Dai Phong Wind Power Plant began in September 2019 and will be completed in July 2020. The project has a total capacity of 50 MW installed. The Dai Phong Investment Development Joint Stock Company, The Blue Circle, and AC Energy are the project’s investors. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: Dai Phong Wind Power Plant project

South Korea – Tra Vinh Wind Power Plant Project (V1.1)

The South Korea- Tra Vinh Wind Power Plant Project (V1.1) began construction in December 2019 and is expected to be finished in September 2021. The project has a total capacity of 48MW installed. Tra Vinh 1 Wind Power Company Limited is the project’s investor (TWPC). PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing, operation, and COD for the power plant as part of this project.

See more: South Korea – Tra Vinh Wind Power Plant Project

Hanbaram 1 and 2 Wind Power Plants Projects

The construction of the Hanbaram 1 and 2 Wind Power Plants began in January 2021 and will be completed in September 2021. The project has a total capacity of 117MW installed. Hanbaram Wind Power Joint Stock Company is the project’s investor. PC1 provides legal services, technical design, procurement, construction, development, production, installation, testing of lines and substations, and COD for the power plant as part of this project.

See more: Hanbaram Wind Power Plants Projects

Hung Hai Wind Power Plant Project

Hung Hai wind power

Construction on the Hung Hai Wind Power Plant began in January 2021 and was finished in October 2021. The project has a total capacity of 100 MW installed. Hung Hai Wind Power Joint Stock Company and BBG Group are the project’s investors. PC1 is responsible for legal services, technical design, procurement, construction, development, production, installation, testing of lines and substations, and COD for the power plant as part of this project.

See more: Hung Hai Wind Power Plant Project

IAPet Dak Doa Wind Power Plant project

The project for the IAPet Dak Doa Wind Power Plant began in March 2021 and ended in October 2021. The project has a total capacity of 199MW installed. TRE Group Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, construction, development, manufacture, installation, and testing of lines and substations, and COD for the power plant as part of this project.

See more: IAPet Dak Doa Wind Power Plant project

Lien Lap Wind Power Plant project

The project for the Lien Lap Wind Power Plant began in April 2020 and was completed in September 2021. The project has a total capacity of 48MW installed. Lien Lap Wind Power Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, building, development, production, installation, testing, and the entire factory, and COD of the entire power plant in this project.

See more: Lien Lap Wind Power Plant project

Phong Huy Wind Power Plant project

The construction of the Phong Huy Wind Power Plant began in April 2020 and completed in September 2021. The project has a total capacity of 48MW installed. Phong Huy Wind Power Joint Stock Company is the project’s investor. PC1 is in charge of legal services, technical design, procurement, building, development, production, installation, testing, and COD of the project.

See more: Phong Huy Wind Power Plant project

Phong Nguyen Wind Power Plant project

Construction on the Phong Nguyen Wind Power Plant began in April 2020 and will be completed in September 2021. The project has a total capacity of 48MW installed. Phong Nguyen Wind Power Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, building, development, production, installation, testing, the entire factory, and COD the entire power plant in this project.

See more: Phong Nguyen Wind Power Plant project

IA Bang 1 Wind Power Plant Project

The construction of the IA Bang 1 Wind Power Plant began in October 2020 and is expected to be finished in October 2021. The project has a total capacity of 50MW installed. Gia Lai Electricity Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, building, development, production, installation, testing, the entire factory, and COD the entire power plant in this project.

See more: IA Bang 1 Wind Power Plant Project

Tan Phu Dong Wind Power Plant Project (Nearshore)

Tan Phu Dong wind power plant construction began in March 2021 and was finished in October 2021. The project has a total capacity of 50MW installed. Tien Giang Wind Power Joint Stock Company is the project’s investor. PC1 is responsible for legal services, technical design, procurement, building, development, production, installation, testing, the entire factory, and COD the entire power plant in this project.

See more: Tan Phu Dong Wind Power Plant Project

Infrastructure projects

Construction of urban railway in Ho Chi Minh City: Ben Thanh-Suoi Tien Line (Line 1)

The Ben Thanh – Suoi Tien railway project began on June 1, 2019 and is scheduled to be finished on June 1, 2022. The project is 19.7 kilometers long in total. The Ho Chi Minh City Urban Railway Project Management Board is the project’s investor (MAUR). PC1 is the general contractor on this project and is responsible for the following works:

  • The electrical installation of the entire power supply system for the project with two 110kV underground cables
  • Installing all transformer stations to supply 1500 VDC rectifier current for the trains of the Metro Ben Thanh-Suoi Tien project
  • Carrying out wiring installation for all communication and signal systems of the project.

See more: Ben Thanh-Suoi Tien Line

Why should you choose an EPC PC1 general contractor?

PC1 Group has become a pioneer in the fields of renewable energy plant and Infrastructure projects general contractor after nearly 60 years of construction and development with high expertise. Customers and investors have given the company their trust and appreciation for its extensive experience in supporting large-scale power plant projects. Aside from optimally satisfying equipment and techniques, PC1 also has a team of highly qualified experts and construction consultants who ensure construction progress and technical standards.

As a result, by becoming a PC1 partner, customers will receive the best incentives for solutions ranging from design to equipment supply, installation, operation, and maintenance. Furthermore, PC1 is always committed to bringing prestigious and high-quality works, as well as ensuring the progress of the works for customers and investors.

If you are looking for an EPC professional contractor, please contact PC1 Group using the information provided below. We are prepared to accompany your company until the project is completed in order to achieve the best possible results.

PC1 GROUP JOINT STOCK COMPANY

  • Tax code: 0100100745; Ticker symbol: PC1
  • Building CT2-No. 583 Nguyen Trai, Thanh Xuan, Hanoi, VN
  • Solution hotline: 0981.119.120
  • Email: epc@pcc1.com.vn

Leave a Reply

Your email address will not be published.